March 14, 2007 |
|
The site is marked out with paint using a laser transit.
Forms are then made out of wood and anchored with steel pins.
Notice that the foreground is deeper than the background. The gutter angle is being set right from the start.
|
March 22nd, 2007 |
|
The excavation is nearly completed, but is interrupted by rain.
|
March 22nd, 2007 |
|
The deepest part of the gutter can be seen carved into the upper wall.
|
March 22nd, 2007 |
|
The pile of dirt is quite large and about as shocking as I thought it would be.
|
March 22nd, 2007 |
|
The two excavators used to do the dirty work.
|
March 23rd, 2007 |
|
I missed most of the under pool plumbing work as it was all completed in a day.
The propane canister is part of a torch used to bend the large 4" pipe used for the returns and drains.
|
March 23rd, 2007 |
|
Here are the large 4" PVC drains, returns, and surge pipes. They set me up with the smallest pump that would
create a boil (more on that later) in the pool, but plumbed it so I could get a much larger pump, if desired.
|
March 23rd, 2007 |
|
Shown are the large returns, surge, and main drains, and the gray electrical conduit for the lighting, and
the smaller Polaris pipe and auto-fill in the surge tank.
|
March 23rd, 2007 |
|
The location of the equipment pad.
|
March 23rd, 2007 |
|
Down the middle are the returns while the two drains form a cross in the center. The surge tank is the
formed up area in the foreground. The idea is that the main drains are typically nearly off and the returns
create a boil in the center of the pool that forces floating debris into the gutters at the sides. The pool
skims incredibly well.
|
March 23rd, 2007 |
|
The two drains and their intersection and one return stub.
|
March 23rd, 2007 |
|
The stub for the Polaris.
|
March 23rd, 2007 |
|
Looking towards the surge tank.
|
March 23rd, 2007 |
|
A wall cavity for a pool light. Three poool lights would have been better, but hindsight is 20/20
and those lights are expensive.
|
March 30th, 2007 |
|
The rebar for the gutters.
|
March 30th, 2007 |
|
More rebar and dobies.
|
March 30th, 2007 |
|
Yet more dobies to space the rebar from the ground.
|
March 30th, 2007 |
|
Rebar cutting and bending equipment.
|
March 30th, 2007 |
|
Lots of progress putting the rebar in.
|
March 30th, 2007 |
|
|
March 30th, 2007 |
|
Here you can see the gutter taking shape. The far end of the gutter is shallower than the near end which
quickly carries the water to the surge pit.
|
March 30th, 2007 |
|
The painted rebar spaces the steel from the dirt and is removed once the steel is complete.
|
March 30th, 2007 |
|
8"x8" grid of steel.
|
March 30th, 2007 |
|
Here is a look at the shallow end of the gutters. This end of the pool is also the shallower end at 4 feet deep.
|
March 30th, 2007 |
|
The steel installation is complete.
|
March 30th, 2007 |
|
The autofill and surge pit suction line.
|
March 30th, 2007 |
|
The surge pit and the pool wall are two separate walls, so the gunite will be twice as thick here.
|
March 30th, 2007 |
|
Gutter detail and dimension markings.
|
March 30th, 2007 |
|
Gutter detail and dimension markings.
|
March 30th, 2007 |
|
Pool light enclosure detail with cover. The cover will protect the inside from the gunite spray.
|
March 30th, 2007 |
|
The rebar for the bench. The bench gets wider at the bottom.
|
March 30th, 2007 |
|
The Polaris fitting.
|
March 30th, 2007 |
|
A different look at the pool light and the wire holding the fixture straight.
|
March 30th, 2007 |
|
A shot of the completed steel pointed towards the surge pit.
|
April 7th, 2007 |
|
In preparation for the gunite spray, piano wire is strung to indicate the walls of the pool and of the gutter.
Piano wire is very strong stuff and can be stretched very tight. It works well for removing windshields too.
Once the gunite is sprayed, it will be troweled with large steel trowels. The wire is strong enough to be trowled over
and is how the gunite guys know where the wall surfaces should be. The pool guys do the wire layout as the gunite
guys don't really appear to know how it should all come together. For me, how the gutters were precisely formed
was the great mystery of the construction process. I had thought that styrofoam would be inserted in the gutter
after the bottom was sprayed, but the wire is the elegant solution.
|
April 7th, 2007 |
|
The surge pit drains are inserted. After the gunite is complete, extensions are attached that guide
the water down into the tank. I suspect that the water falling noise could have been made quieter
by running the extensions at a 45 degree angle, but mine are set at 90 degrees. Since they extend below the water
level in the surge pit, the noise ocurrs mostly inside the tubes. If noise is heard from the surge tank, it's the
auto-fill running to keep the pool level up.
|
April 7th, 2007 |
|
The worker in the foreground is using pieces of wallboard to provide a surface under the forms for
the gunite to spray against.
|
April 7th, 2007 |
|
The pipe in the left side of the surge pit is the overflow drainage in case it rains and the pool needs
to shed some water. An extension is later added to this pipe that reaches down towards the bottom of the pit.
|
April 7th, 2007 |
|
The first step in the gunite spraying is to tack down the steel in the middle and at the corners so that
it doesn't move around.
|
April 7th, 2007 |
|
More tacking down of the steel cage.
|
April 7th, 2007 |
|
Spraying of the edges starts.
|
April 7th, 2007 |
|
|
April 7th, 2007 |
|
The pool guys making sure that everything goes as planned. These two men did all of the work on the pool except the gunite and plaster.
|
April 7th, 2007 |
|
The pool guys describe the gunite phase as carving sandcastles. Here you can see that the floor of the pool hasn't
been sprayed yet. The Polaris connector can be seen, and some strange black holes are carved in the side of the pool. The holes
are carved into the pool to support scaffolding.
|
April 7th, 2007 |
|
More carving.
|
April 7th, 2007 |
|
Here you can see the wallboard being used as a backer for the gunite. The inside
of the gutter will not be easily seen through the grating, however, it does need
to be smooth so as not to impede the flow of water.
|
April 7th, 2007 |
|
Another shot of the piano wire put to good use.
|
April 7th, 2007 |
|
The end of day one. The gunite guys will have to come back tomorrow.
|
April 7th, 2007 |
|
Here the pool wall can be seen as distinct from the surge pit wall that has yet to be sprayed.
|
April 7th, 2007 |
|
The exit stairs are taking shape.
|
April 7th, 2007 |
|
The completed exit stairs. Also visible is the grounding wire for the lane rope anchors and for the
starting block anchors.
|
April 7th, 2007 |
|
We were instructed to get enough soaker hose to completely encircle the pool to aid in the curing of the gunite.
Although the water isn't turned on in the photo, it works perfectly at keeping every bit of the gunite wet. Gunite
is very porous and when it's hot out, a stream from a hose will disappear in to the pool wall.
|
April 14th, 2007 |
|
The plumbing to the equipment pad is completed with the addition of the solar piping and sensor wire conduit.
The electrical conduit to the electrical panel is also present along with some EMT conduit that is there just
to hold up the subpanel when it is installed later.
|
April 14th, 2007 |
|
Another view of the two large solar pipes and the gray sensor wire conduit. The remaining gray conduit continues
straight towards the far side of the house where the main breaker panel is located. This work had to be scheduled
after the gunite to prevent the pool wall from caving in when the backhoe was used to dig the trench. The first
third of the concrete patio was also covered with soil. My irrigation pipe to the enclosed planters can be seen
sticking up. Two years prior I had layed over 1,000 feet of irrigation pipe.
|
April 26th, 2007 |
|
It rained some more while we were installing the drainage pipe. The pool guys left the trench unfilled for us
while we installed some proper drain pipe to solve a drainage problem that we've had since we moved in. My first
attempt used the closest stormwater drain on the side of the house, however, that only left about 8.5 inches of
drop over 125 feet. I also used that *really* bad black corrugated drain pipe. It's alwful stuff and I'll never
use it again. The next year, my second attempt involved taking some of the dips out of the corrugated drain pipe
and installing some straight sections of drain pipe.
|
April 26th, 2007 |
|
The current drainage solution was suggested by the pool guys. They used a
transit level to determine that I had 26
inches of drop if I went all the way out to the front of the house. While that would have presented a significant
digging challenge for me in past years, the pool guys had dug a trench for the electrical conduit, so we dug it out
a bit more and made use of that. The hardest part was digging out in front of the house as that is where the
services come in and had to be all hand dug. In the end, we only found the cable TV service during the dig.
|
April 26th, 2007 |
|
We used 3" drain pipe from each of the four down spouts feeding into a 4 inch line that ran across the flat part of
the yard. That pipe has a high point in it that causes one down spout's runoff to run to the original stormwater
drain I was using, while the other three down spouts' water travels out to the street. The run out to the street
is through 6 inch drain pipe. That is because we get significant runoff from the neighbor's houses and the 4 inch
pipe would otherwise be innudated. A drain pipe can only be run up to 3/4 full before the flow rate slows significantly.
|
April 26th, 2007 |
|
The location of the six inch pipe. I had researched some solutions for trapping water and soaking it back into
the ground, but they are very expensive and I wasn't sure that the small distance between the patio and pool decking
would support the underground solutions. As the pool guys found out, we also have hardpan a couple of feet under the
surface. I may look into rain barrels next year.
|
April 26th, 2007 |
|
The primary difference between this pool and any other pool is the precision required to get the water to break all
around the pool edge. To do that requires a very level edge. But the edge is not flat in the sense of a laser beam,
but instead follows the curviture of the Earth. So instead of a laser level, a
water level is used.
|
April 26th, 2007 |
|
The cement leveling pads are set out at regular intervals and the coping edge and angle edge lengths are affixed
to the top with screws.
|
April 26th, 2007 |
|
The regions between the leveling pads are filled with white thinset mortar.
|
April 26th, 2007 |
|
A corner joint.
|
April 26th, 2007 |
|
Here is what one of the seams look like between lengths of coping.
|
April 26th, 2007 |
|
Here is a cross section view of the hand hold coping. Using this coping prevented us from needing bull nose
tile around the pool. Not only did that save us some money, but it results in a very clean look to the finshed pool.
|
April 26th, 2007 |
|
A template was used to set the hold-down screw spacing. The stainless screws are turned into plastic anchors
set in the gunite. The grating is held to the coping and angle plastic by stainless z-brackets and another
stainless square-drive screw. The grating can be removed.
|
April 26th, 2007 |
|
The grating that we used is typically
used for commerical pools and is called GrateTech. The specific product
is the handhold 14" grate.
|
April 26th, 2007 |
|
A duck showed up a bit on the early side.
|
April 26th, 2007 |
|
Once the coping edge is in place, the gutter is coated with
ThoroSeal.
|
April 26th, 2007 |
|
The big picture.
|
May 9th, 2007 |
|
The coping installation was ocurring at the same time as our drainage installation. And the drainage had to
be completed before the decking could be formed because of the proximity of the two. Here you can see that a cap
is being formed for the surge tank.
|
May 9th, 2007 |
|
The steel being installed for the surge pit cap. The surge tank can be cleaned out via the access hole, but
it's not commonly required. There is a lot of post-construction sediment in there right now, so I may get in
there and clean it out soon.
|
May 9th, 2007 |
|
The concrete patio once again sees the light of day. It needs to be resealed again, but we're waiting for
construction to finish.
|
May 9th, 2007 |
|
A starting block anchor.
|
May 9th, 2007 |
|
Each patio will have a set of stairs. The middle patio is 6" lower than the other two because of the sunken living room.
|
May 9th, 2007 |
|
Wide lumber was used because the side face of the deck will be visible.
|
May 9th, 2007 |
|
The equipment pad forms.
|
May 16th, 2007 |
|
|
May 16th, 2007 |
|
All ready to pour the deck at this point. We're currently starting the installation of the tile, so the pool guys moved on to
the lane rope anchors.
|
May 16th, 2007 |
|
This is the back side of a lane rope anchor.
|
May 16th, 2007 |
|
The model number casting.
|
May 16th, 2007 |
|
The eye hook is stainless and replaceable, but the cup is chromed bronze. If we had it to do again, we
would have used stainless steel rope anchors, like these.
The high pH of our water here combined with the action of the curing plaster led to the anchors being
corroded by the acid poured in the pool to lower the pH. Once the plaster was cured (about 6 months)
the corrosion slowed down or might have stopped.
|
May 16th, 2007 |
|
The anchor waiting for installation.
|
May 16th, 2007 |
|
Another shot.
|
May 16th, 2007 |
|
The finished installation.
|
May 16th, 2007 |
|
Another shot.
|
May 17th, 2007 |
|
Time to pour the deck.
|
May 17th, 2007 |
|
Pumping in the concrete. We opted for a salt finish. The concrete decking won't match the stamped and colored
patios as the decking would end up very hot on the feet.
|
May 17th, 2007 |
|
The starting block anchor distance and height is set.
|
May 17th, 2007 |
|
The surge tank access hole.
|
May 17th, 2007 |
|
|
May 17th, 2007 |
|
The redwood bender board is used to get uniform thickness to the mortar base. The mortar base is required
so that the plaster will be thick enough around the tile. The plaster ends up being 3/8" to 1/2" thick.
|
June 3rd, 2007 |
|
In the pool, the tile progress is going slow. It really could be done in two full days, but I was really
concerned about making a mistake, and was double checking everything. At least the mortar base is down in
the correct place.
|
June 3rd, 2007 |
|
We chose two turtles and two fish mosaics for the end targets.
|
June 3rd, 2007 |
|
After setting the tile, I used a 4" angle grinder with a diamond blade to score a line along both sides of the tile.
I then used a hammer and a brick set to remove the excess mortar. To keep the tile going straight, we used a 72"
long level.
|
June 3rd, 2007 |
|
The line looks bent in this photo because the pool is 2 feet deeper in the center than at the ends.
|
June 3rd, 2007 |
|
The plasterers are responsible for installing the two main drains so that they are centered between the tiles.
|
June 3rd, 2007 |
|
We were doing this after work, so often it was dark out. That led to about 6 feet of the line having to be pulled
up when we followed the wrong chalk line. Fortunately the mortar hadn't set yet.
|
June 3rd, 2007 |
|
The end cross is used by swimmers to judge the timing of flip turns.
|
June 3rd, 2007 |
|
Our turtle and fish targets.
|
June 3rd, 2007 |
|
While we are still finishing the tile, the pool guys have now installed the pool equipment.
|
June 3rd, 2007 |
|
We chose LED pool lights purely for the fun factor.
|
June 3rd, 2007 |
|
With the tiling done, the plastering began. The edges of the coping were taped to prevent damage from
trowels and all the plaster guys put on their spiked shoes.
|
June 3rd, 2007 |
|
Since the gunite is very porus and not very attractive, the plaster is used to waterproof the pool and
to provide some visual interest. We used white plaster largely to keep the pool's temperature down.
We aim for 80 degrees.
|
June 3rd, 2007 |
|
The night before the plaster went in, I discovered some loose tiles. The tile in the center of the pattern
was slightly thicker than the corner tiles and several corner tiles were loose. To check them all, I used
a plastic mallet and tapped every tile. If the tile sounded hollow, made a tapping noise, or a higher pitched
noise, I pulled it up and mortared it back down properly. I'm pretty certain that I got them all. The plaster
guys said that it's common to find loose tiles and they just stick them back on with plaster.
|
June 3rd, 2007 |
|
The air hose attached to the side of the plaster gun kept coming loose so I grabbed a stainless clamp from
my fixit box and let them have it.
|
June 3rd, 2007 |
|
The plastering went much faster than the gunite. I think it only required 3/4 of a day.
|
June 3rd, 2007 |
|
When using the trowels, the plasterers always used an upward stroke on the walls.
|
June 3rd, 2007 |
|
The plaster must set pretty fast because they were moving very quickly once it was sprayed on.
|
June 3rd, 2007 |
|
The returns and drains are set by the plasterers. The large holes around the returns and drains
are simply filled with plaster. The main drains can be offset in any direction to overcome the piping
not being in exactly the right spot. They lined up the main drains with the tile stripe but didn't
line them up with eachother when viewed perpendicular to the stripe. I didn't catch it until they were
set so that is the way they remain.
|
June 3rd, 2007 |
|
|
June 3rd, 2007 |
|
The pool guys hard at work
|
June 3rd, 2007 |
|
The floor being put in.
|
June 3rd, 2007 |
|
The stairs and bench are very nicely finished - probably as nice or nicer than any pool I've been in.
Notice the footwear. The finishers wore either sponges on their feet or shoes made out of tape. Oils
from skin contact will stain the plaster.
|
June 3rd, 2007 |
|
A plasterer cleaning up the marks from his shoes.
|
June 4th, 2007 |
|
A pool should be immediately filled after plaster and
should be continuously filled from the deepest part up to avoid stains on the plaster. If the water
is shut off, a permanant ring will be left in the plaster. Additionally, a sock is put
over the hose ends to prevent erosion of the plaster surface from the running water. During the first
day of filling, care should be taken to prevent dirt from getting into the pool. Since the pool is
44,500 gallons, it took a couple of days to fill.
|
June 3rd, 2008 |
No Photo Yet
|
We bought a solar cover and cover reel recently. The solar cover heats the pool very well and
got us into the pool in May at 72 degrees F. To get the right size, we ordered two 16'x40' covers,
which led to an unexpected problem. Most residential cover reels will not hold 75 or 80 feet of
cover. We ended up finding a Rockies Commercial Junior reel that does the job nicely, but at a
surprising cost.
|